Sector: |
Education |
Client: |
St Peter’s Woodlands Grammar School Inc. |
Value: over $12M
Method: |
Managing Contractor |
“I Have found the entire Pascale team to be cooperative, personable, easily approachable, highly efficient, particularly to documentation processes and timelines, responsive to client's needs, and always accommodating. In addition, I have found them trustworthy and honest in all dealings" Christopher Prance, Principal
Process
Since 2005, Pascale Construction has successfully completed over 25 individual projects at St Peter’s Woodlands Grammar School Inc. These projects are both of major proportions as well as general building works.
Some of the major projects include The Pines Early Learning Centre, The Gillam Building GLA’s Refurbishment, The Millington Building GLA’s Refurbishment, The Thorpe Building upgrade, The Law Smith Administration, Building Upgrade and the significant works carried out for the new RJ Taylor Library and Music Centre.
In particular the Law Smith Building is Heritage Listed and required delicate and a specialized approach to the refurbishment works undertaken.
(photos by Don Brice)
Resolution
The stringent requirements set by the client regarding program and conduct on site has been meticulously adhered to for every project. Program has been critical in many of the projects in particular where the works were required to be conducted and completed during the school’s Christmas shutdown period in readiness for the commencement of the new school year.
Similarly, site coordination and conduct of building works has been critical where the projects were running within the operating school environment.
The preferred procurement method for the vast majority of projects conducted has been on a Managing Contractor arrangement. This has nurtured the collaborative project team approach resulting in very successful outcomes.